Center School Presentations

Notice of Special Meeting by Town Council

January 27th at 5:30 p.m.
Information from finalists attached

Pursuant to the direction of Christopher Pia, Chair, the Stratford Town Council will conduct a special meeting on January 27, 2022 in Council Chambers of Stratford Town Hall, 2725 Main Street, Stratford, CT at 5:30 p.m. for the presentation of proposals by the two finalists for the Stratford Center Transit Oriented Development Project.

Presentations – stratford center transit oriented development project will be made by the two finalists:

  • Romano Brothers Builders
  • Spirit Investment Partners – Kaali-Nagy Properties

Presentations and all information on the two finalists may be found at the following website:

https://www.stratfordct.gov/qcontent/NewsFeed.aspx?FeedID=3088

1. Spirit Proposal:

PROPOSAL PREPARED FOR:

TOWN OF STRATFORD

Attn: Phillip Ryan, Purchasing Agent 2725 Main Street, Rm 104
Stratford, CT 06615

RFP #2022-01 SUBMITTED October 25, 2021

A Co-Development of Spirit Investment Partners and Kaali-Nagy Properties
45 East Putnam Avenue, Suite 106
Greenwich, CT 06830
Phone: (212) 331-8354

www.spiritinvestmentpartners.com

www.Kaali-nagy.com

October 25, 2021

Ms. Mary Dean

Economic & Community Development Director Town of Stratford
2725 Main Street,
Stratford, CT 06615

RE: RFP # 2022-01 Stratford Center Transit Oriented Development Project

 45 East Putnam Avenue Suite 106
Greenwich, CT 06830
(203) 966-8254

 

Dear Mary Dean: 

Once again, we would like to thank you and your fellow committee members for the opportunity to be involved in this RFP. As you know, we have put in a considerable amount of time over the past few months and welcome the opportunity to hopefully seeing this project through.

After some careful consideration, including updating our rents and fine tuning our projected cash flows, we are please to present a revised financial offer that is enclosed in this submission. Further, we have reviewed the appraisal submitted to us on October 18th and believe our current offer is more in line with the information included after considering the goals and requests set forth in the RFP.

Included in this submission you will find the following updated information:

  • Proposed Sources and Uses
  • Updated 10-year Cash Flow with associated footnotes
  • Proposed 10-Year PILOT, which is in accordance with Section 191-11 of the Stratford Tax Incentive Program
  • Revised Letter of Intent

As previously mentioned, we would welcome the opportunity to provide any supporting schedules that include more detail of the information enclosed.

On behalf of the Spirit-KN team, we thank you again and look forward to your feedback.

Sincerely,

Scott D. Zwilling Principal, Spirit KN

 

Project Budget | Sources & Uses

Project Budget

The Project Budget outlines the various costs associated with the development and the associated sources of funds needed.

Spirit KN are well financed and highly confident in its ability to capitalize this project. We are happy to discuss our financials with the Town of Stratford.   

10 Year Cash Flow Model

Proforma Footnotes

 

  1. All units at Sutton Place project to be 100% market rate with the following unit

  1. Market Standard 0% Loss to Lease
  2. Assumed pre-leasing of 30% at opening of property, while leasing up at 15 units / month afterwards until reaching a stabilized occupancy of 95%. In Deal Year 3, we’ve assumed various amounts of free months on a twelve-month lease, from 2 months, to 1 month, to half a
  3. Stabilized Occupancy of 95%
  4. Assumes 1 Model Unit
  5. Assumes a 5% delinquency and collection loss
  6. Projecting a $5 trash fee and full reimbursement of water and sewer costs. All other utilities will be paid directly by
  7. Includes $50 / month per parking space of below ground structure, pet income, application fees, late fees, and a

$55/month amenity fee. Assumptions are comparable to similar properties in the area.

 

 

Proforma Footnotes

  1. Comparable to market standards
  2. Assumes staffing of a property manager, a leasing agent, a superintendent, and a maintenance Compensation in-line with market comparables.
  3. Advertising and Marketing is in-line with previously managed Additional marketing funds for the initial lease up period are capitalized in the construction budget.
  4. Turnover costs in-line with market Assume 0 turns in the first year, and 20% in year two, 40% thereafter.
  5. Repairs and Maintenance costs are in-line with newly constructed
  6. Contract Service costs are in-line with newly constructed buildings
  7. Market Standard 75% Management Fee.
  8. Utility Estimates are in-line with comparable properties in the
  9. Insurance quotes have been priced out with Lockton Companies at $400 /
  10. Property Taxes have been vetted with multiple tax specialists familiar with Fairfield County and local tax See next page for the full tax projection and corresponding Tax Incentive Proposal.

Proposed Pilot

Given the cost of the subterranean parking garage and other restriction imposed upon the proposed development, Spirit KN is requesting a PILOT schedule, which is in accordance with the Town of Stratford Tax Incentive Program.

 

RE: RFP #2022-01 – Stratford Center Transit Oriented Development Project Revised LOI

 

Dear Mary Dean:

This letter sets forth the terms and conditions under which Spirit Investment Partners/Kaali-Nagy Properties and/or its assignees (the “Purchaser”) is willing to proceed with the acquisition of the

  • acre of land, formerly known as the Center Elementary School Site, located at 1000 East Broadway, Stratford, CT 06615 from the Town of Stratford (the “Seller”). Upon execution by both parties, this letter shall serve as the basis for the legal counsel of Purchaser to prepare a definitive Purchase and Sale Agreement (the “Agreement”) per the price and conditions below:
  1. Purchaser’s Project Purchaser intends to develop the Property with 160 multifamily units and related amenities (the “Purchaser’s Project”).
  2. Price The purchase price for the Property shall be One Million Six Hundred Twenty Five Thousand ($1,625,000), all cash at closing, less deposits and subject to customary adjustments and prorations (the “Purchase Price”). The final land price shall be adjusted proportionately based on the number of units approved by governmental
  3. Inspection Period The Purchaser shall have an inspection period of ninety (90) days following execution and delivery of a purchase and sale contract (the “Contract”) and delivery of the last of the due diligence items (the “Inspection Period”), during with time Purchaser may cancel the Contract at Purchaser’s absolute discretion by written notice to A detailed list of due diligence items will be provided for in the Contract. Seller shall deliver all of said items in its possession and control.
  4. Deposits All deposits shall be applicable to the Purchase Price at Final Closing and delivered as follows:
    Within two (2) business days from full execution of the Contract, Purchaser shall deposit the sum of Thirty-Seven Thousand Five Hundred Dollars ($37,500) (“Initial Deposit”) to be held in escrow in an interest-bearing account by the Title Company during the pendency of the Agreement. The Initial Deposit shall be fully refundable prior to the close of the Inspection

In the event the Purchaser elects to proceed with the purchase beyond the Inspection Period, Purchase shall place a second deposit of Thirty-Seven Thousand Five Hundred Dollars ($37,500) (“Additional Deposit”, plus Initial Deposit collectively known as the “Earnest Money”) to be held in escrow by the Title Company in an interest-bearing account by the Title Company during the pendency of the All interest earned shall become part of the Earnest Money. After the Earnest Money becomes non-refundable, subject to the conditions in Section 6 and 7, if the Purchaser fails to consummate the transaction as required under the terms of the Agreement, said Earnest Money shall be retained by Seller as full and final liquidated damages. If Seller fails to consummate the transaction as required under the terms of the Agreement, the Earnest Money shall be returned to Purchaser and Purchaser shall be entitled to such remedies as are set forth in the Purchase Agreement, including specific performance.

  1. Closing The closing under the Contract shall occur sixty (60) days after the Final Approvals are in place for the development of Purchaser’s Project, unless Purchaser waives this condition in writing. Purchaser, at its election, may extend the closing for three (3) consecutive 30-day period by increasing the Deposit by $25,000 for each such extension. These extension deposits ($75,000 if all three are exercised) shall be nonrefundable and shall be applied to the Purchase Price.
  2. Final Approvals The Purchaser, at Purchaser’s expense, will diligently seek the Final These include zoning (including site plan approval, variances, special use permits, and the like, as applicable under municipal zoning) so as to allow for Purchaser’s Project to be constructed, with all appeals periods having lapsed. Once the site plan approval becomes final, Purchase, at Purchaser’s cost, will prepare construction/engineering drawings for the Project and will present the same to appropriate governmental and quasi-governmental agencies for approval and for other approvals as may be required. Once those plans are approved and building permits are available (contingent only upon payment of applicable fees) with all appeal period having lapsed, the Project will be deemed to have the “Final Approvals” and Purchaser will proceed to closing. If Final Approvals include less than 160 multifamily units, Purchaser may terminate the Contract and obtain the return of the Earnest Money.
  3. Conditions Precedent to Closing The following matters shall be conditions to Purchaser’s obligation to close and the Earnest Money becoming non-refundable.
  4. Purchaser shall have obtained Final Approvals. If Purchaser does not receive the Final Approvals within Twelve (12) months (the “Approval date”) from the end of the inspection period, Purchaser may unilaterally extend the Approval Date for six months, provided Purchaser evidences to Seller that it has submitted to governmental agencies construction plan and specifications for the same. If the Final Approvals are not obtained by the eighteenth (18th) month following the end of the Inspection Period, either party may terminate the Contract with written notice, provided Purchaser may negate a Seller termination notice by electing to proceed to Closing and waive the condition precedent of Final If Purchaser elects to terminate the agreement, all Earnest Money shall be refunded to Purchaser within ten (10) days on notice of election to terminate

PILOT and incentive approval for the said Project by the Town of Stratford that is acceptable to Purchaser.

  1. There will be no moratoria imposed by any federal, state or local governments or agencies thereof or private or public utilities that would prevent delay or impair any aspect of Purchaser’s development of the Property and issuance of appropriate permits for Purchaser’s
  2. All utilities for the Project will be available to the site in sufficient capacity to service Purchaser’s Project and available for “tap in”.
  3. Seller shall convey title to the Property to Purchaser subject only to restrictions and other matters of title existing and/or agreed upon prior to the end of the Inspection Period, none of which may preclude Purchaser’s
  4. The physical condition of the Property shall not have materially changed from the end of the Inspection Period until the closing.
  5. Cooperation Seller will fully cooperate with and assist Purchaser in securing all necessary approvals for Purchaser’s Purchaser will be responsible for all costs associated with the Final Approvals. Purchase will be responsible for all costs associated with the design of the Project. Closing costs will be shared jointly by Purchaser and Seller in customary fashion for Stratford, Connecticut.
  6. Brokers The parties represent and warrant to each other that they have not dealt with any real estate brokers, salesman, or finders to whom a brokerage commission is

Seller and Purchaser shall provide appropriate mutual indemnification language with respect to claims of real estate brokers and/or real estate agents in the Contract.

This letter is an expression of interest only, and none of the provisions hereof shall be binding on either party unless and until set forth in the Contract and signed by both parties. This offer will expire unless accepted by Seller and a signed counterpart of this Letter is received by us on or before 5:00 PM Eastern Standard Time on or before September 8th, 2021.

Notwithstanding the foregoing, by its execution below, Seller hereby agrees that it will not enter into active discussions concerning the development of the Property with a third party, will not market the Property to any other person, and will not execute any other letter of interest or other agreement with any potential buyer after the execution date of this Letter of Interest for thirty days. If the foregoing is agreeable, please sign below and return a copy to Purchaser and we will instruct our attorneys to prepare a purchase contract appropriate in a transaction of this nature. In connection with the same please provide us with a copy of the existing survey, owner’s title insurance policy, and hard copies of title exceptions.

We look forward to working with you to complete this transaction.

Sincerely,

Scott Zwilling Managing Principal

 

Purchase Price Analysis with Proposed PILOT
 

Appraised Value of Land

 

$3,000,000

Number of Units Appraisal is Based Upon 150
Appraised Value Per Unit $20,000
Appraised Land Value Per Unit $20,000
Number of Units if Surface Parking (no garage) 139
Total Value of Land if Sold with No Restrictions (garage, spaces to city, etc.) $2,780,000
Cost of Below Grade Garage (Hard and Soft Costs) (1) ($6,889,520)
Asphalt Cost if Surface Park (no garage) $200,000
Public Park Construction Cost ($500,000)
Value of Park Maintenance (2) ($100,000)
Value of Additional Units (3) $420,000
Value of Additional Rent on Garage Spaces (4) $562,000
Value of Ongoing Maintenance for BOE Below Grade Spaces (5) ($300,000)
 

Net Value of Land

 

($3,827,520)

Land Purchase Price Offered to Town ($1,625,000)
Net Cost of Land ($5,452,520)
Present Value of PILOT Benefit (10 yrs) @ 5% discount rate $4,569,476
Difference ($883,044)
  • 206 below grade spaces x $33,444.27 per space
  • $5,000 per year @ 5% cap rate
  • 160 units – 139 units = 21 additional units x $20,000/unit
  • 156 below grade parking spaces x $15/month ($50/month for garage – $35/month for surface) @ 5% cap rate
  • $15,000 in operating cost per year at a 5% cap rate

 

 Parking Count                                                                                                                

 

 

Public Street Parking on Sutton Avenue

# Spaces

9

Garage Spaces (units on Sutton Ave) 18
Below Grade Garage Spaces *** 156
Visitor Spaces 4
Total Residential Spaces 187
Board of Ed Surface Spaces 30
Board of Ed Below Grade Spaces *** 50
Total Non-Residential Spaces 80
*** Total Below Grade Spaces 206

 

MINIMUM PARKING REQUIRED PER ZONING ***
# Units Min. Pkg Total Min. Spaces
Studio 8 1 8
1-Bed 102 1 102
2-Bed 44 1.25 55
3-Bed 6 1.5 9
Total 160 174

 

*** Based on TOD Overlay

2. Romano Brothers Proposal:

August 17, 2021

To: The Center School Property Selection Connnittee Attn: Ms. Karen Sportini
Economic and Connnunity Development Town of Stratford
2725 Main Street, Room 104
Stratford, CT 06615

Re: RFP #2022-01
Development of Town Owned Property
Stratford Center Transit Oriented Development Project Romano Brothers Builders, LLC

Dear Connnittee Members,

On behalf of Team Romano, we submit a revised proposal to address the items identified in the emails from Ms. Mary Dean to Mark Romano on July 26 and July 27, 2021. For reference, a copy of the emails are attached hereto. A Supplemental Executive Sunnnary and ten (10) copies of same with one (1) flash drive are also included with this letter. The Romano Team looks forward to meeting with the Connnittee on August 31, 2021 at 9:00 a.m. in the Stratford Town Council chambers.

RFP #2022-01
Stratford Center TOD Project

Q Mark Romano
Romano Brothers Builders, LLC
6 Fransway
Shelton, CT 06484
(203) 650-4800

Romano Brothers Builders, LLC Revised Proposal
Supplemental Executive Summary

Revised Proposal Based Upon Comments from the Committee

Romano Brothers Builders, LLC (“Romano”) hereby submit this Supplemental Executive Summary in response to comments from the Committee. See comments attached as Exhibit A.

The Entity

Addressed in prior Executive Summary.

The Team

Addressed in prior Executive Summary.

Proposed Revised Purchase Price

Romano offers $1,540,000.00 to purchase the Property.

Housing Units

Romano Builders proposes to build a total of 154 housing units with a total of 196 bedrooms based upon a 3.6 acre parcel in the TOD zone. 20 of the units will be two-bedroom flats in four unit townhouses, and an additional 134 units in a single four-story building where 14 units will be studios.

The revised building footprint is 36,608 square feet; therefore, at 4 stories, it is 146,423 square feet. The bedroom count is as follows:

1. 2 studio / 21 one / 6 two
2. 4 studio / 25 one/ 6 two
3. 4 studio/ 26 one/ 5 two
4. 4 studio / 26 one/ 5 two

In total, 14 studio/ 98 one/ 22 two= 134 units/ 156 bedrooms requiring 140 spaces. Flats on Sutton, 20 units / 40 bedrooms requiring 25 spaces.

98 units are proposed to be one bedroom units and 22 units are proposed to be two bedroom units. The townhouses are proposed to face Sutton Avenue with 5 four-unit townhouses facing Sutton Avenue; two buildings to the left and three to the right of the proposed greenscaped park area (“Sutton Park”) that will be accessible to the public as well as to occupants of the development at no cost to the Town.

The townhouses and main building are designed to be in keeping with the neighborhood and nearby historical buildings, namely, the First Congregational Church of Stratford building located at 2301 Main Street. The motif from the original proposal will be in keeping with this revised proposal.

The four-story apartment building will also include a business center, a recreation room, and a fitness center.
Adjustments to the number of proposed units may be made; however, there may be a conesponding adjustment to the purchase price. See Revised Site Plan attached as Exhibit B.

Parking

It is proposed that a total of 260 units of parking be provided. See the following calculations:

A total of 245 spaces are required for the proposal, broken down as follows:

Board of Education:
• Surface Spaces 20
• Underground Spaces 60
Residential:
• Studio/one-bedroom units (112@ 1/unit) 112
• Two-bedroom units (42 @ 1.25/unit) 53
Total: 245 spaces
A total of 260 spaces has been provided as follows:
• Underground 18l
• Surface @BOE 20
• Surface @ garage entrance 8
• Along access drive 30
• At building entry plaza 21
Total: 260 spaces See Parking Plan attached as Exhibit C.

Ninety percent of the units above the at-grade parking will have a garage space available. It is likely that this would be more than adequate considering reduced car ownership in a T.0 .D. multifamily development. Therefore, assuming a 90% mixed-use or T.O.D. parking need for the multifamily building, the required below grade residential parking is 121 spaces. This combined with the 60 Board of Education spaces equals the total 181 underground parking spaces provided. The developer is prepared to assign 60 underground spaces for use by the Board of Education and will conform to the Town’s Zoning Regulations for the residential development with 15 excess spaces being provided.

Romano does not intend to seek compensation for the Town’s use of these spaces.
Maintenance and snow and ice clearing will be the responsibility of Romano.

Romano believes that the townhouses and greenscaping along the western edge of the proposed park will substantially screen any onsite above grade parking from the view of the surrounding neighborhood.

There is an increase in subtenanean parking which has an impact on the price Romano can offer for the property so that there is a corresponding adjustment to the proposed purchase price. See page one. Additionally, a tax abatement will be required, to cover the cost of the additional subtenanean parking spaces.

Affordable Units

Addressed in prior Executive Summary.

SUTTON PARK

An 80 x 120 foot public access park to be created and maintained by Romano at no cost to the Town.

Dog Park

If desired, Romano intends the inclusion of a dog park for use by tenants at no cost to the Town. A proposed location is shown on plans but this location may be changed.

Economic Impact

Addressed in prior Executive Summary.

MomDUSE

Team Romano does not believe that commercial use – retail, business, office or otherwise, will be successful on the subject Property. However, upon reflection, the Board of Education’s use of the property is, essentially, a mixed use of the property.

Tax Abatement

The increased underground parking greatly drives up the cost of the project. For this revised Proposal Romano requests the application of the tax abatement schedule as set forth in Section 191-11 of the Stratford Town Code entitled Incentive Programs, for cost of improvement,
$20,000,000.00 or greater.

This schedule is as follows:

During the period of construction, but not greater than eighteen (18) months, or such additional time as may be extended by the Tax Partnership Screening Committee, but not to exceed six (6) additional months. Given the scope of construction, although not anticipated, it is possible that additional time will be required, but see Development Time Line below, or (2) until the receipt of Certificate of Occupancy, whichever shall occur first: 100% exempt, then following such period of issuance of Certificate of Occupancy:

Year 1: up to 100% Exempt;
Year 2: up to 100% Exempt;
Year 3: up to 100% Exempt;
Year 4: up to 80% Exempt;
Year 5: up to 70% Exempt;
Year 6: up to 60% Exempt;
Year 7: up to 50% Exempt;
Year 8: up to 40% Exempt;
Year 9: up to 30% Exempt;
Year 10: up to 20% Exempt.

Traffic Flow

Addressed in prior Executive Summary.

Pedestrian Flow

Addressed in prior Executive Summary.

The TOD Zone

The Romano Proposal is consistent with the TOD zone requirements and will not require variances from the Zoning Board of Appeals. The Proposal will provide an alternative to the traditional single family home environment.

In addition, the Romano Proposal will lead to market growth in Stratford Center. It will be the redevelopment of an unutilized property. The Proposal will create an environment that encourages walking and bicycling as transit use, thereby reducing auto dependency.

The Romano Proposal will provide a range of housing options for people at different stages of life and will be consistent with enhancing the nearby streetscape. It will, of course, be within walking distance of the Stratford Train Station and the GBTA bus line.

Subcontractors

A. Addressed in prior Executive Summary.

Resources Required from the Town of Stratford

It is not anticipated that any resources will be required from the Town of Stratford other than that standard administrative services for constmction related activities. The Town of Stratford will not be involved financially in the project’s capital status. However, tax abatement, as set forth above will be required.

Development Time Line

The construction is proposed to be formed in a single phase. A conservative estimate for time is six (6) months for land use approvals; six (6) months for design, bidding and contracting; and one and a half (1½) yearn to build out.

Public Outreach

It is anticipated that the Romano team, during the land use approval phase, will plan and conduct at least two informational sessions for the public and local businesses.

 

 

Author

RELATED ARTICLES

1 COMMENT

LEAVE A REPLY

Please enter your comment!
Please enter your name here

Most Popular

Recent Comments

Zoltan Toman on Curious by Nature
Zoltan Toman on Holiday Cheer
Seamus Matteo on An Expression of Gratitude
raul gerena on The Stories We Tell
Barbara Heimlich on Zombie Barbie Returns to Library!
Cynthia Loynd on A Tribute to Teaching
Angelique D Jones PhD on Jahseh Martinez Funeral
Barbara Heimlich on When Bird Carving Was Cool
Rhonda Voos on Retail Politics
Dinushka De Silva on Retail Politics
David Chess on Letter from the Editor
David Chess on Letter from the Editor
Stephanie Philips on Letter from the Editor
Richard Sylvester on Blue Lion Jazz in Stratford
Kenneth G Matteau on CT Assembly Bill HB 5004
Lisa on Cash for Trash
Sharon Arsenault Heckley on Combating Rumors and Gossip
Karen P. Burke on Special Education Costs
Paula Sweeley on Tariff Talk
David Chess on A Woman of Substance
Ashley Lotzer on Goody Bassett Exonerated!
Ted van Griethuysen on In Memoriam: Richard Pheneger
Paula Sweeley on It’s Pie Time of Year!
Paula Sweeley on It’s Pie Time of Year!
Paul A. Tavaras on Election Roundup
Zoltan Toman on My Veterans Quilt
Ted van Griethuysen on Have You Voted?
Zoltan Toman on Mark Your Calendar
Ben on Trash Update
Taxpayer's Worst Nightmare on Interview with Dr. Uyi Osunde
Seamus Matteo on The Long Haul Trucker
Seamus Matteo on Letter to the Editor
Seamus Matteo on Stratford Street Takeover
Paula Sweeley on Stratford Street Takeover
Seamus Matteo on Longshoremen’s Strike
Jas. M. McHale on Library Gets State Funding
David Chess on Bankruptcy Filing Denied
Joe LaBash on LET THEM EAT … PIZZA?
Matthew Whitney Lechner on To Protect and Serve
Janeen Navarro on Love is Love, Stratford, CT
Moshe Rabeinu on Transportation Updates
Ted van Griethuysen on General Lafayette’s Last Visit
John Kamenitsky on Interview with Dr. Uyi Osunde
E roig on Trash Update
E roig on Trash Update
Mallory Benjamin on Trash Update
sick of stupid people on Trash Update
Tara May on Trash Update
Patricia DeGemmis on Trash Update
Connie Kristu on Trash Update
James serreti on Trash Update
Debbie on Trash Update
David Chess on Teen Violence
Andy Byrne on Spotted Lantern Fly
William J. Chiarenzelli on Traffic Safety Cameras
Mary Budrawich on Spotted Lantern Fly
David Chess on Norah
Beverly Blackwell on Statement by Dr. Uyi Osunde
Paula Sweeley on Statement by Dr. Uyi Osunde
Dee Hiatt on The Poetry Corner
David Chess on The Poetry Corner
david chess on The Stories We Tell
Paula Sweeley on Trash Update
Lou on Trash Update
Janine Aggott on Trash Update
David Chess on The Poetry Corner
James on Trash Update
Randall Stewart on Army Engine Plant Plans
Micharchangel on Trash Update
Dominic on Trash Update
Ted van Griethuysen on Letter To The Editor
Cathy B. on Trash Update
Ted van Griethuysen on A Cautionary Teacher’s Tale
David Chess on The Poetry Corner
Gary Brian Tanguay on Blues on the Beach
Jas. M. McHale on New Trains for Amtrak
JM McHale on Memorial Day Parade
Lisa Carroll-Fabian on BOE Finance Committee Special Meeting
David Chess on The Poetry Corner
Chris Johannessen on The School Budget De-Mystified
Paula Sweeley on BOE Budget Not Set In Stone
David Chess on The Poetry Corner
Henry Bruce on Stratford BOE Being Sued
Sara B on Whose Money is it?
Dr. Karen P. Burke on Dr. Uyi Osunde Press Release
Greg Carleton on Stratford BOE Being Sued
Paula Sweeley on Stratford BOE Being Sued
Ted van Griethuysen on Dr. Uyi Osunde Press Release
Greg Reilly on Animal Cruelty
David Chess on The Poetry Corner
Paula Sweeley on ALPHA
Ted van Griethuysen on Letters To The Editor
Barbara Heimlich on Teakwood Estates
Barbara Heimlich on Letters To The Editor
Tina Manus on Letters To The Editor
Ben Leone on Teakwood Estates
Marca Leigh on Teakwood Estates
Paula Sweeley on Teakwood Estates
Julie Lawrence on A Fight for Equality
David Chess on The Poetry Corner
Dee Hiatt on The Poetry Corner
Paula Sweeley on Bankrupt Stratford Part 3
Barbara Heimlich on ALPHA
on ALPHA
Barbara Heimlich on Bankrupt Stratford Part 2
Barbara Heimlich on ALPHA Program Staff Members
Barbara Heimlich on Librarians Matter
Kara Flockhart on Librarians Matter
Paula Sweeley on ALPHA Program Staff Members
Cheryl Dwyer on Bankrupt Stratford Part 2
Barbara Heimlich on Bankrupt Stratford Part 1
Barbara Heimlich on Reinstate Dr. Uyi Osunde
Paula Sweeley on Bankrupt Stratford Part 1
Paula Sweeley on BOE Budget
Trish on BOE Budget
David Chess on BOE Budget
David Chess on Chairman Interview
Paula Sweeley on BOE Budget
Barbara Heimlich on Celebrate Stratford 2024 Events
Trish on Budget Meeting
Barbara Heimlich on Budget Meeting
Caitlin A on Budget Meeting
David Chess on Budget Meeting
Barbara Heimlich on Letter To the Editor
Barbara Heimlich on Snow in Will’s Garden
Jocelyn Ault on The Poetry Corner
Ruben Matos on Letter To the Editor
Ted van Griethuysen on Letter To the Editor
David Chess on The Poetry Corner
Ted van Griethuysen on Snow in Will’s Garden
Michael Kalweit on Stratford: The Stories We Tell
Barbara Heimlich on Why We Love to Hate I-95
Barbara Heimlich on Town Council Meeting-January 8
Patricia H O'Brien on The Poetry Corner
Barbara Heimlich on Poetry Corner
Barbara Heimlich on Hawley Lane Development Back
Chris Johannessen on Hawley Lane Development Back
David Chess on Poetry Corner
Greg Reilly on New Year – New Housing
donna m conroy on New Year – New Housing
Patrick Hennessey on Poetry Corner
David Chess on The Poetry Corner
Gail M. Liscio on Fire and Ice Festival
Teresa Kona on Happy Thanksgiving
James M McHale on Night Safety Program
Ben Leone on Why a Theater??
Ben Leone on Shakespeare Theatre
David Chess on The Stories We Tell
Ted van Griethuysen on The Stories We Tell
Ben Leone on Broken Promises
Paula Sweeley on The Heart of the Matter
Ted van Griethuysen on Opinion: Shakespeare Theatre
Ted van Griethuysen on Why a Theater??
Barbara Heimlich on Town Council Candidates
Barbara Heimlich on Shakespeare Park Sundial
David Chess on The Poetry Corner
donna conroy on Goody Bassett Exonerated
John Florian on Poetry Corner
Danny Cook on Town Council Candidates
David Chess on Poetry Corner
Paula Sweeley on Letter to the Editor
Paula Sweeley on Know the Vote!
Paula Sweeley on Democrat Meet and Greet
David Chess on The Poetry Corner
Paula Sweeley on Shakespeare Presentation
David Chess on The Poetry Corner
David Chess on The Poetry Courner
David Chess on Mileage Tax
Trish on Prove It!
Donna Marie Conroy conroy on Stratford’s Horseshoe Crabs
David Chess on Shakespeare Theatre
David Chess on The Poetry Corner
Patty Spermer on District 6 Election Forecast
Barbara Heimlich on Slipper Shells Invade Long Beach!
Paula B Sweeley on The Soap Box
Paula Sweeley on Attack Garden Pests
Paula Sweeley on Attack Garden Pests
Paula Sweeley on Letters To The Editor
Paula Sweeley on Center of Controversy
Paula Sweeley on Center of Controversy
Nels C Pearson on “Nature Is Only Sleeping”
Janet Cocca on Champagne ?????
manustina@gmail.com manus on Letter To The Editor: Center School
Paula Sweeley on You better watch out
Paula Sweeley on Stratford Crier Voter Guide
Paula Sweeley on Remington Woods
Paula Sweeley on Stratford Crier Voter Guide
Paula Sweeley on Sunset Boulevard
Karen P Burke on Make Your Voice Heard
Paula Sweeley on Celebrating Pride Month
Paula Sweeley on Tennis and Trees
Patricia on Save Our Salt Marsh
Patricia on Obituary: Joan Joyce
Paula Sweeley on Tennis and Trees
Paula Sweeley on Update: Democracy In Action
Paula Sweeley on Update: Democracy In Action
Tom G on The Soap Box
Woodie on The Soap Box
Paula Sweeley on Tennis and Trees!
Paula Sweeley on Tennis and Trees!
Paul! Sweeley on Tennis and Trees!
Bill OBrien on Auld Lang Syne
Bill OBrien on Auld Lang Syne
Patricia on Auld Lang Syne
Trish on Stratford Stars
Paula Sweeley on Town Council District 7
Paula Sweeley on Letters To The Editor
Patricia on Let the Games Begin!!
Paula Sweeley on Let the Games Begin!!
Barbara J Bosco on Never Forget!
Paula B Sweeley on Never Forget!
Paula B Sweeley on Center School Update
Barbara Heimlich on Where Am I?
Paula Sweeley on June is Gay Pride Month
Paula Sweeley on June is Gay Pride Month
Rosemary Martin Hayduk on “This is Not Field of Dreams.”
Jorge castro on Drive-Thru Food Pantry
Jorge castro on Drive-Thru Food Pantry
JESS P. GELTNER on Know Your Town: First District
Paula Sweeley on Candidate: Dr. James Simon